Project name: Green Ports Madeira (ID: 101079667)
Project value: € 1 196 000,00 (with 50% EU co-funding)
The Green Ports Madeira project
APRAM - Administração dos Portos da Região Autónoma da Madeira, S.A., together with EEM - Empresa de Electricidade da Madeira, S.A., applied to the European funding mechanism CEF - Connecting Europe Facility to carry out a project that aims to study the preconditions for decarbonising the three major ports in the Autonomous Region of Madeira - the Port of Funchal, the Port of Caniçal and the Port of Porto Santo.
This application was supported by a number of relevant regional and international stakeholders, including the Regional Government, Funchal City Council, the operator of the regular passenger transport line between Madeira and Porto Santo and CLIA - Cruise Lines International Association, representing shipowners in the cruise industry.
The application received a very positive evaluation from the EU because it reflects the commitments made under the European Union's climate objectives on the road to climate neutrality, as well as allowing the study of strategies for other ports that face specific constraints often encountered by the outermost regions due to their remote geographical location.
The Green Ports Madeira project was approved, with a budget of € 1 196 000,00 and 50% of EU financial support.
Objectives
The main objective of the Green Ports Madeira project is to study the technical and economic feasibility of implementing solutions for supplying electricity to ships berthed in the region's three main ports. Adjacent to this main objective are studies on energy production from renewable sources, as well as the implementation of infrastructures to supply alternative fuels to ships visiting the region.
The project also aims to develop strategies to find sustainable solutions for the Madeira port terminals, in particular with regard to alternative energy sources for supplying ships at berth and multimodal low-emission solutions to reduce emissions of greenhouse gases in the port areas.
Action Plan
Green Ports Madeira is planned to last 24 months and is therefore divided into a number of tasks aimed at achieving its objectives. Among these objectives is the development of various studies: